Step-by-Step Rack Installation Guide

Pre-Installation Requirements

Before rack installation begins, ensure the following prerequisites are met:

TC Series Installation (Welded)

TC Series racks arrive as pre-assembled units. Installation is straightforward:

1
Position uprights — Use crane to place upright assemblies at marked floor locations. Use shims for leveling.
2
Anchor to floor — Drill holes for M20 chemical anchors. Install anchors per manufacturer specs. Torque to 250 Nm.
3
Verify alignment — Check plumb (vertical) with spirit level. Check spacing between uprights matches drawings ±5mm.
4
Test arms — Extend and retract each arm under no-load conditions. Verify smooth operation, proper end-stop engagement.
5
Load test — Apply 110% rated load to each arm. Hold for 10 minutes. Measure deflection. Must be within L/200 limit.

TE Series Installation (Assembled)

TE Series requires full on-site assembly. Allow 2-3× more time than TC Series. Follow the numbered component labels and assembly drawings provided with each shipment. Key differences: upright sections must be bolted together with specified torque values, horizontal bracing installed before arm mounting, and all bolted connections must be re-torqued after 30 days of operation.

Post-Installation Checklist